      "id": "PRE-001",
      "source": "pre_generation",
      "section": "4.1, 4.2, 4.3",
      "category": "interfaces",
      "question": "Are there any interfaces with the public, environment, or other works on or near the site? Include any traffic management arrangements and constraints. Attach a picture if available.",
      "validated_wpp_value": "",
      "priority": "high",
      "answer": "The construction of the invert slab interfaces with other activities including M&E installation by Wingate and PCC erection managed by EKFB. There are no identified public interfaces for these works. Traffic management arrangements include designated routes for all construction traffic, speed limits for vehicular movements, and the use of wheel wash facilities for vehicles leaving the Chipping Warden Site",
      "answered_at": "2026-04-14T19:32:38.458891+00:00",
      "images": [
        "PRE-001_579ccc2e.png",
        "PRE-001_0441ce83.jpg"
      ]
    },
    {
      "id": "PRE-002",
      "source": "pre_generation",
      "section": "5.9",
      "category": "emergency",
      "question": "What is the nearest hospital with A&E facilities? Please provide the name, address, and a picture or map of the route from the work site.",
      "validated_wpp_value": "",
      "priority": "high",
      "answer": "The nearest hospital with A&E facilities is Horton General Hospital. It is located at Oxford Road, Banbury, Oxfordshire, Postcode OX16 9AL.",
      "answered_at": "2026-04-14T19:32:38.458903+00:00",
      "images": [
        "PRE-002_5a23b248.png"
      ]
    },
    {
      "id": "PRE-003",
      "source": "pre_generation",
      "section": "2.3",
      "category": "material",
      "question": "Do you have an approved materials list for this project? If so, please provide it so the AI can use the correct materials. Otherwise the AI will use standard materials for this work type.",
      "validated_wpp_value": "",
      "priority": "medium",
      "answer": "N/A",
      "answered_at": "2026-04-14T19:32:38.458906+00:00",
      "images": []
    },
    {
      "id": "PRE-004",
      "source": "pre_generation",
      "section": "1.2",
      "category": "logistics",
      "question": "What is the access route and method of transport from the main storage/laydown area to the work front? Attach a picture if available.",
      "validated_wpp_value": "",
      "priority": "high",
      "answer": "The access route to the work front is through the tunnel, using whichever bore is currently open to traffic. Method of transport from the storage or prefabrication areas to the work front includes the use of tractors and trailers, telehandlers, or multi-directional sideloaders.",
      "answered_at": "2026-04-14T19:32:38.458908+00:00",
      "images": [
        "PRE-004_5bf98aa4.png",
        "PRE-004_57338a2f.png"
      ]
    },
    {
      "id": "PRE-005",
      "source": "pre_generation",
      "section": "1.2",
      "category": "logistics",
      "question": "Where is the designated storage/laydown area for materials near the work front? Attach a picture if available.",
      "validated_wpp_value": "",
      "priority": "high",
      "answer": "The designated storage area for reinforcement steel delivered from the factory is located close to the prefabrication yard. Additionally, safe storage or park areas are designated inside the tunnel to feed the work front once access is granted. The reinforcement can also be stored on the invert slab preceding the one currently under construction, provided the concrete strength has been confirmed by an engineer",
      "answered_at": "2026-04-14T19:32:38.458910+00:00",
      "images": []
    }
  ]
}