  "generated_at": "2026-03-19T18:21:28.305313+00:00",
  "draft_path": "data/output/wpp_20260318_080133.json",
  "validated_wpp_path": "/Users/aya/git/crewAI/source_docs/03_Datasets & Inputs/03_RAMS/Tunnel/1MC12-EKF-CL-MST-CS10-000772 C03.docx",
  "status": "pending",
  "total_questions": 7,
  "answered": 0,
  "questions": [
    {
      "id": "Q001",
      "source": "gap_analysis",
      "section": "1.1, 1.10, 1.2, 1.6, 1.7, 1.9, 10, 3, 4.1, 6, 7, 8, 9, 9.2",
      "category": "logistics",
      "question": "Where will the welfare facilities be located in relation to the working area, and how will operatives access them safely during the works? Please describe any restrictions, walking routes, and arrangements for moving between the workfront and welfare area.",
      "validated_wpp_value": "",
      "priority": "high",
      "answer": null,
      "answered_at": null
    },
    {
      "id": "Q002",
      "source": "gap_analysis",
      "section": "1.1, 1.10, 1.2, 1.6, 1.7, 1.9, 10, 3, 4.1, 6, 7, 8, 9, 9.2",
      "category": "resource",
      "question": "What is the intended crew composition and working pattern for these works? Please describe the key operatives, any specialist subcontractors or plant operators required, and whether the task will be completed in one shift or over multiple shifts.",
      "validated_wpp_value": "",
      "priority": "high",
      "answer": null,
      "answered_at": null
    },
    {
      "id": "Q003",
      "source": "gap_analysis",
      "section": "1.1, 1.2, 1.7, 1.9, 7",
      "category": "method",
      "question": "Where will the key equipment be positioned during the works, and how will it be set up and accessed on site? Please describe the arrangement for plant such as pumps, lifting equipment, generators, and any restrictions on their location or movement.",
      "validated_wpp_value": "",
      "priority": "high",
      "answer": null,
      "answered_at": null
    },
    {
      "id": "Q004",
      "source": "gap_analysis",
      "section": "1.1, 1.10, 1.2, 1.7, 1.9, 10, 3, 4.1, 6, 7, 8, 9, 9.2",
      "category": "contingency",
      "question": "What are the contingency plans if something goes wrong during the works, such as plant failure, delayed deliveries, adverse weather, or failed test results? Please describe the stop-work, replacement, repair, rescheduling, and escalation arrangements.",
      "validated_wpp_value": "",
      "priority": "high",
      "answer": null,
      "answered_at": null
    },
    {
      "id": "Q005",
      "source": "gap_analysis",
      "section": "1.7",
      "category": "material",
      "question": "Which project-specific temporary works drawings, design packages, permits, hold points, or check sheets apply to this work package, and what approvals are required before the work can proceed or be loaded?",
      "validated_wpp_value": "",
      "priority": "high",
      "answer": null,
      "answered_at": null
    },
    {
      "id": "Q006",
      "source": "gap_analysis",
      "section": "1.6, 1.7, 7",
      "category": "safety",
      "question": "What are the site-specific fire and emergency arrangements for this work area, including the location and availability of firefighting equipment, who will act as the Fire Marshal, and how emergency contact details and first aid arrangements will be briefed to the team?",
      "validated_wpp_value": "",
      "priority": "high",
      "answer": null,
      "answered_at": null
    },
    {
      "id": "Q007",
      "source": "engineer_input_flag",
      "section": "1.1",
      "category": "method",
      "question": "Confirm \u2014 membrane or covering?",
      "validated_wpp_value": "",
      "priority": "high",
      "answer": null,
      "answered_at": null
    }
  ]
}